Subsystem with similar functionality as of "Unit Delay"

1 visualización (últimos 30 días)
Anubhav Routray
Anubhav Routray el 12 de Mzo. de 2023
Comentada: Paul el 13 de Mzo. de 2023
I want to replace all the 'UnitDelay ' blocks in a model with a subsystem which would have the functionality of 'UnitDelay' block.
I want such a subsystem because the initial condition to the 'Unit Delay' block should be passed from a custom block(for example a constant block or From workspace block) as the initial conditions are changed frequently. I have the initial conditions stored in an array. Any help is appreciated. I am using MATLAB 2020a.
(Also I can not use the old Unit Delay with IC block because of my requirement limitations)
  6 comentarios
Paul
Paul el 12 de Mzo. de 2023
"I change the value of IC from 5 to 6 and observe some change."
Are you changing the value of the IC from 5 to 6 while the simulation is running, or after the simulation with IC=5 is complete and you want to use IC = 6 for the next simulation?
Anubhav Routray
Anubhav Routray el 12 de Mzo. de 2023
I want to use the IC =6 for the next simulation

Iniciar sesión para comentar.

Respuestas (1)

Paul
Paul el 12 de Mzo. de 2023
Does the Delay block meet the need? It can accept an IC from an external source and is externally resettable.
  4 comentarios
Anubhav Routray
Anubhav Routray el 13 de Mzo. de 2023
Editada: Anubhav Routray el 13 de Mzo. de 2023
I completely agree with your solution. However the scenario that I explained was an example. I have around 500 UDs in the complete model and it is not a feasible way to change the field of every block. I have already created a script where the value of the new IC is ready to be fed automatically. I need a subsytem to replace the all the UDs in the model with a means to feed the new ICs (which I am thinking to be from a "From Workspace" block, but I am open to any other suggestion).
Paul
Paul el 13 de Mzo. de 2023
I still don't understand why the Delay block (doc page link in he original Answer) doesn't fit the need. It can support a delay of 1, i.e., a unit delay and also supports an externally supplied initial condition.

Iniciar sesión para comentar.

Categorías

Más información sobre Subsystems en Help Center y File Exchange.

Community Treasure Hunt

Find the treasures in MATLAB Central and discover how the community can help you!

Start Hunting!

Translated by