How to implement resource schedules in SimEvents?

2 visualizaciones (últimos 30 días)
Jose Parga
Jose Parga el 11 de Oct. de 2017
Comentada: Jose Parga el 17 de Oct. de 2017
Is there a way to schedule resources in SimEvents? I am trying to model a manufacturing system were there are operators and machines. The operators can only work at certain hours but the machines can theoretically work all day. How would I implement this?
Thanks for any feedback!

Respuestas (1)

Meeshawn Marathe
Meeshawn Marathe el 17 de Oct. de 2017
Editada: Meeshawn Marathe el 17 de Oct. de 2017
Please go through this SimEvents example on Job Scheduling and Resource Estimation for a Manufacturing Plant. It will give you an overview of modeling a manufacturing plant too.
  1 comentario
Jose Parga
Jose Parga el 17 de Oct. de 2017
I have looked at it but this is a continuous schedule. I need something were the people only work 8 hours a day rather than 24/7. Is there a function block to implement this? Or would I need us a gate block and every 16 hours it causes the process involving people to stop?

Iniciar sesión para comentar.

Categorías

Más información sobre Discrete-Event Simulation en Help Center y File Exchange.

Community Treasure Hunt

Find the treasures in MATLAB Central and discover how the community can help you!

Start Hunting!

Translated by