Simulink test manager 'Parallel Test Execution' is stopping with error
Mostrar comentarios más antiguos
I want to decrease the time of Simulation for running 30 Test harness. I installed 'Parallel Computing tool box' and enabled 'Parallel' in Test Manager. I tried to run the test file. All the test harness are failing with the following error.
Error evaluating expression 'T_sample_control' for 'FixedStep' specified in the Configuration Parameters dialog for block diagram 'HM_Harness_4_1_1'.
Undefined function or variable 'T_sample_control'.
Variable 'T_sample_control' does not exist.
If the 'Parallel' is disabled all the harness are running fine. What might be the problem?
1 comentario
Varunjith Vijayan
el 25 de Abr. de 2018
Respuestas (1)
Anmol Pradeep Bhargava
el 4 de Mayo de 2018
1 voto
Hi Varunjith,
As per my understanding parallel pool workers do not inherit the current environment so if you load parameters before starting the parallel execution the workers won't inherit those values. Although, you can assign all values in Callback section of the test file in Simulink Test Manager. This way when you run the test file in parallel mode the workers will be able to load callbacks and get the parameters.